If you are still struggling to prepare for passing 70-178 certification exam, at this moment IT-Tests.com can help you solve problem. IT-Tests.com can provide you training materials with good quality to help you pass the exam, then you will become a good Microsoft 70-178 certification member. If you have decided to upgrade yourself by passing Microsoft certification 70-178 exam, then choosing IT-Tests.com is not wrong. Our IT-Tests.com promise you that you can pass your first time to participate in the Microsoft certification 70-178 exam and get Microsoft 70-178 certification to enhance and change yourself.
IT-Tests.com not only provide the products which have high quality to each candidate, but also provides a comprehensive after-sales service. If you are using our products, we will let you enjoy one year of free updates. So that you can get the latest exam information in time. We will be use the greatest efficiency to service each candidate.
IT-Tests.com can provide professional and high quality products. It is the industry leader in providing IT certification information. To selecte IT-Tests.com is to choose success. IT-Tests.com's Microsoft 70-178 exam training materials is your magic weapon to success. With it, you will pass the exam and achieve excellent results, towards your ideal place.
The curtain of life stage may be opened at any time, the key is that you are willing to show, or choose to avoid. Most of People who can seize the opportunityin front of them are successful. So you have to seize this opportunity of IT-Tests.com. Only with it can you show your skills. IT-Tests.com Microsoft 70-178 exam training materials is the most effective way to pass the certification exam. With this certification, you will achieve your dreams, and become successful.
Exam Code: 70-178
Exam Name: Microsoft Microsoft Project 2010, Managing Projects 70-178
Free One year updates to match real exam scenarios, 100% pass and refund Warranty.
Updated: 2013-08-27
Feedbacks of many IT professionals who have passed Microsoft certification 70-178 exam prove that their successes benefit from IT-Tests's help. IT-Tests's targeted test practice questions and answers to gave them great help, which save their valuable time and energy, and allow them to easily and smoothly pass their first Microsoft certification 70-178 exam. So IT-Tests.com a website worthy of your trust. Please select IT-Tests, you will be the next successful IT person. IT-Tests.com will help you achieve your dream.
70-178 (Microsoft Project 2010, Managing Projects) Free Demo Download: http://www.it-tests.com/70-178.html
NO.1 You need to set the default constraint type for all new tasks to As Late As Possible. What should you
do?
A. Select all tasks, and then click Layout.
B. In the Options dialog box, enable the New Tasks are effort driven check box.
C. Select all tasks, and then set the constraint type to As Late As Possible.
D. In the Project Information window, from the Schedule From drop-down list box, select Project Finish
Date.
Answer: D
Microsoft 70-178 certification 70-178
NO.2 You use bottom-up scheduling. You need to group four consecutive tasks in a major phase. You
highlight the four tasks. Which command should you use?
A. Outdent
B. Fill Down
C. Insert Summary
D. Move Task
Answer: C
Microsoft answers real questions 70-178 70-178 test answers
NO.3 You manage a project that specifies all constraint types to As Soon As Possible. You discover that one
of your key tasks is scheduled to end prior to the targeted finish date. You need to display the targeted
finish date on the default Gantt chart. What should you modify in the Task Information window?
A. Set the Deadline date field.
B. Set the Constraint date field.
C. Set the Finish date field.
D. Select the Mark task as milestone check box.
E. Select the Display on Timeline check box.
Answer: A
Microsoft test answers 70-178 70-178 70-178 70-178
NO.4 The first major phase of your project is scheduled for a duration of 45 days. However, you do not have
task information for other phases. You need to indicate that the duration of the entire project is 200 days.
What should you do?
A. Select the Project Summary Task option.
B. Select the Summary Tasks option.
C. Create a manually scheduled summary task.
D. Update the project calendar.
Answer: C
Microsoft certification 70-178 certification 70-178 study guide 70-178 exam simulations
NO.5 You need to view Task ID 0 on your project plan. What should you do?
A. On the Advanced tab of the Project 2010 options, select Show Status Bar.
B. On the Format tab, select Summary Tasks.
C. On the Format tab, select Project Summary Task.
D. Insert a new Summary Task.
Answer: C
Microsoft study guide 70-178 70-178 70-178
NO.6 A section of your project contains only a summary task along with four subtasks and a milestone. You
discover that the section is located in the incorrect phase and has the incorrect Work Breakdown
Structure (WBS) numbering. You need to move the section to another phase of the project. You also need
to ensure that the section reflects the correct WBS numbering. What should you do?
A. Select the summary task and change the scheduling mode to Manually Scheduled.
B. Select the entire section and click Move Task.
C. Drag the summary task.
D. Modify the start and finish dates of the summary task.
Answer: C
Microsoft 70-178 70-178 70-178 70-178 braindump
NO.7 You manage a project according to the schedule as shown in the exhibit.
You need to set the Task Mode for task 4 to be the same as task 6. What should you do?
A. Create a task dependency from Task 4 to Task 6.
B. Set Task 4 as critical.
C. Add a 1 day lead to Task 4.
D. Set Task 4 as manually scheduled.
Answer: D
Microsoft pdf 70-178 70-178 70-178 exam 70-178 practice test
NO.8 You manage several projects. Each project has shared resources and work distribution. You need to
ensure that you can adjust the workload for specific resources used across multiple project schedules.
What should you do?
A. Enable the Load Summary Resource Assignments option. Then, select the Level Resource function on
each project.
B. Open the individual schedules and use the Visual Reports option. Then, use the Resource Usage view
to manually modify resource Work.
C. Open a blank project and select Insert Subproject for each project schedule. Then, use the Level
Resource function for selected resources.
D. Open the shared Resource Pool for each project schedule. Then, use the Level Resources function.
Answer: C
Microsoft 70-178 test questions 70-178 exam 70-178 70-178 exam prep
NO.9 The project you manage has only part-time resources. The part-time resources work four hours a day
from Wednesday through Saturday. You need to create a new calendar and set the calendar as the
default for your project. Which two actions should you perform? Each correct answer presents part of the
solution.
A. Select the part-time calendar from the Change Working Time window.
B. Set the calendar type to part-time for all tasks.
C. Select the part-time calendar from the Project Information window.
D. On the Project tab, Select Change Working Time, and then click Create New Calendar.
E. Change the Calendar type in the Project Options dialog box.
Answer: CD
Microsoft 70-178 70-178 test answers 70-178
NO.10 You have a Project 2010 schedule that contains the following tasks:
Inactive tasks
Manually scheduled tasks
Manually scheduled summary tasks
Tasks that contain strikethrough font
You want to save the schedule as a Project 2007 project. You need to ensure that no new milestones are
created. What should you do.?
A. Change all inactive tasks to active tasks.
B. Change all tasks that contain strikethrough font to tasks that include normal font.
C. Change all manually scheduled summary tasks to automatic scheduling.
D. Change all manually scheduled tasks to automatic scheduling.
Answer: C
Microsoft 70-178 70-178 exam
If you are an IT staff, do you want a promotion? Do you want to become a professional IT technical experts? Then please enroll in the Microsoft 70-178 exam quickly. You know how important this certification to you. Do not worry about that you can't pass the exam, and do not doubt your ability. Join the Microsoft 70-178 exam, then IT-Tests.com help you to solve the all the problem to prepare for the exam. It is a professional IT exam training site. With it, your exam problems will be solved. IT-Tests.com Microsoft 70-178 exam training materials can help you to pass the exam easily. It has helped numerous candidates, and to ensure 100% success. Act quickly, to click the website of IT-Tests.com, come true you IT dream early.