The curtain of life stage may be opened at any time, the key is that you are willing to show, or choose to avoid. Most of People who can seize the opportunityin front of them are successful. So you have to seize this opportunity of IT-Tests.com. Only with it can you show your skills. IT-Tests.com CompTIA JK0-017 exam training materials is the most effective way to pass the certification exam. With this certification, you will achieve your dreams, and become successful.
IT-Tests.com has been to make the greatest efforts to provide the best and most convenient service for our candidates. High speed and high efficiency are certainly the most important points. In today's society, high efficiency is hot topic everywhere. So we designed training materials which have hign efficiency for the majority of candidates. It allows candidates to grasp the knowledge quickly, and achieved excellent results in the exam. IT-Tests.com's CompTIA JK0-017 exam training materials can help you to save a lot of time and effort. You can also use the extra time and effort to earn more money.
If you do not know how to pass the exam more effectively, I'll give you a suggestion is to choose a good training site. This can play a multiplier effect. IT-Tests.com site has always been committed to provide candidates with a real CompTIA JK0-017 certification exam training materials. The IT-Tests.com CompTIA JK0-017 Certification Exam software are authorized products by vendors, it is wide coverage, and can save you a lot of time and effort.
Compared with other training materials, why IT-Tests.com's CompTIA JK0-017 exam training materials is more welcomed by the majority of candidates? First, this is the problem of resonance. We truly understand the needs of the candidates, and comprehensively than any other site. Second, focus. In order to do the things we decided to complete, we have to give up all the unimportant opportunities. Third, the quality of the product. People always determine a good or bad thing based on the surface. We may have the best products of the highest quality, but if we shows it with a shoddy manner, it naturally will be as shoddy product. However, if we show it with both creative and professional manner, then we will get the best result. The IT-Tests.com's CompTIA JK0-017 exam training materials is so successful training materials. It is most suitable for you, quickly select it please.
Exam Code: JK0-017
Exam Name: CompTIA (CompTIA E2C Project+ Certification Exam)
JK0-017 (CompTIA E2C Project+ Certification Exam) Free Demo Download: http://www.it-tests.com/JK0-017.html
NO.1 Which of the following would be a direct output of the initiating process group? (Select TWO).
A. Project charter
B. Project management plan
C. Statement of Work (SOW)
D. Work Breakdown Structure (WBS)
E. Preliminary scope statement
Answer: AB
CompTIA exam simulations JK0-017 pdf JK0-017 test JK0-017
NO.2 Which of the following tools would be used to determine the relationship between two changed
variables?
A. Scatter diagram
B. Qualitative risk analysis
C. Ishikawa diagram
D. Monte Carlo analysis
Answer: C
CompTIA questions JK0-017 exam dumps JK0-017 JK0-017 exam simulations
NO.3 Which of the following can the project manager do to manage scope creep?
A. Be open minded to new ideas to the project.
B. Be flexible about what needs to be done to complete the project.
C. Be specific when defining project objectives in the project plan.
D. Be positive when approached with changes to ensure customer satisfaction.
Answer: C
CompTIA JK0-017 JK0-017 test answers JK0-017 exam simulations
NO.4 Which of the following describes a work breakdown structure (WBS) dictionary?
A. A high level requirements document used to create the WBS.
B. An alphabetical listing of WBS components detailing their associated project schedule dependencies
C. An organizational reference defining how WBS levels must be decomposed.
D. A supporting document that provides more detail for the WBS components.
Answer: D
CompTIA questions JK0-017 JK0-017 JK0-017
NO.5 There are three teams assigned to the same project. Two of the project teams are ahead of schedule;
however, the product does not meet the needed quality standards. The third project team is behind
schedule, but their product meets the quality standards. Which of the following should be the NEXT step
for the project manager?
A. Inform the stakeholders that the project is behind schedule.
B. Meet with the teams to clarify the schedule and the quality standards expected.
C. Crash the schedule to meet the project timeline.
D. Fast track the schedule to complete the project on time without impacting the quality of the product.
Answer: D
CompTIA certification training JK0-017 JK0-017 exam JK0-017 JK0-017
NO.6 Which of the following is described when a company requires version control of project documents?
A. Decision oversight
B. Regulatory compliance
C. Internal process compliance
D. Change management controls
Answer: D
CompTIA JK0-017 braindump JK0-017 original questions JK0-017 JK0-017 JK0-017 demo
NO.7 In an attempt to make a deadline, a North American project manager is able to procure emergency
funding for additional people. The resources are located in Europe. Which of the following project
components will have to be updated to reflect working with a new time zone location?
A. Communication plan
B. Risk management plan
C. Work Breakdown Structure (WBS)
D. Project scope statement
Answer: C
CompTIA JK0-017 JK0-017 JK0-017 JK0-017
NO.8 Given the following information:
Pessimistic estimate is 30 days
Most Likely estimate is 15 days
Optimistic estimate Is 10 days
Which of the following is the expected duration for this scheduled activity?
A. 11 days
B. 17 days
C. 25 days
D. 29 days
Answer: C
CompTIA test JK0-017 exam JK0-017 JK0-017 JK0-017
NO.9 Which of the following represents the EAC of an ongoing project with an AC of $100,000, a CV of
$10,000 and an ETC of $50,000?
A. $90,000
B. $140,000
C. $150,000
D. $160,000
Answer: C
CompTIA exam simulations JK0-017 JK0-017 questions JK0-017
NO.10 A project manager has been informed that a project deliverable must be completed by September 1st.
Which of the following BEST describes this situation?
A. Project assumption
B. Project constraint
C. Project risk
D. Acceptance criteria
Answer: B
CompTIA JK0-017 JK0-017 braindump JK0-017 JK0-017
NO.11 One of the team members assigned to a project is not performing well. The team member is new and is
not experienced in the type of work involved with this project. Which of the following is the BEST response
to this situation?
A. Ask other members to help.
B. Assign the team member to another project.
C. Talk to the team member to encourage better performance.
D. Arrange for training for the team member
Answer: D
CompTIA original questions JK0-017 JK0-017 test answers
NO.12 The project cost performance index is 1.2 and the project manager has spent $71,248 dollars to date.
The project is currently 50 percent complete. Which of the following is the earned value (EV)?
A. $35,624.00
B. $59,373.33
C. $71,243.00
D. $35,497.60
Answer: A
CompTIA JK0-017 JK0-017 JK0-017 JK0-017
NO.13 Which of the following is the purpose of a milestone schedule?
A. A detailed summary of the project milestones that need to be achieved.
B. A summary level timetable of the major project milestones.
C. A summary of the anticipated milestones and the issues identified for the project.
D. A detailed summary of the anticipated milestones and risks identified for the project.
Answer: A
CompTIA original questions JK0-017 JK0-017
NO.14 Which of the following are common causes of project team conflict? (Select TWO).
A. Project schedule
B. Competing resource demands
C. Project budget
D. Varying work styles
E. Time zone difference
Answer: BD
CompTIA braindump JK0-017 JK0-017 test
NO.15 A project has been cancelled during the execution phase. Which of the following steps should be
taken?
A. Continue to work the project.
B. Finish the project charter and project plan.
C. Complete lessons learned document.
D. Develop the project transition plan.
Answer: C
CompTIA original questions JK0-017 exam JK0-017 exam simulations JK0-017
NO.16 Three of the team members are having a conflict with each other. Which of the following steps should
the project manager take to minimize the conflict?
A. Resolve the conflict by terminating the team members.
B. Ignore the conflict and keep working on the project.
C. Encourage the team members to resolve the conflict.
D. Ask the project sponsor to resolve the conflict.
Answer: C
CompTIA certification JK0-017 certification training JK0-017 JK0-017 exam dumps JK0-017
NO.17 Which of the following is the method for determining the critical path of a project?
A. Determine the BAC of a project and the AC at completion; calculate the difference.
B. Examine the project schedule and determine the two most critical milestones: then calculate the total
time form the start of the first determined milestone to the end of the second.
C. Examine the project schedule and place all scheduled activities on one time-line, regardless as to
whether they are being implemented in parallel. Then calculate the total time taken.
D. Examine the project schedule and calculate the total time taken for all scheduled activities, from
commencement of the project to closure, with zero float.
Answer: D
CompTIA certification training JK0-017 JK0-017 JK0-017 exam dumps JK0-017
NO.18 A project change is approved by the Change Control Board that modifies the project scope. Which of
the following is the NEXT step that the project
A. Construct a detailed plan to implement the change.
B. Analyze the Impact of the change request.
C. Document the request in the change control log.
D. Request a meeting with the project sponsor to discuss scope creep.
Answer: A
CompTIA JK0-017 JK0-017 exam
NO.19 Two SMEs disagree with the designed plan for a particular component. The project will be delayed if
the plan is not approved today. The project manager demands the SMEs work together to incorporate
their modifications by the close of business today. Which of the following resolution techniques was used?
A. Negotiating
B. Forcing
C. Smoothing
D. Compromise
Answer: B
CompTIA braindump JK0-017 JK0-017 practice test
NO.20 A project manager notices that status meetings are poorly attended and that one or two team member
try to dominate the meetings. Which of the following should the project manager do to make the project
status meetings more productive? (Select TWO).
A. Include agenda items in the meeting invitation.
B. Ensure that the meetings start and end on time.
C. Provide criticism to poor team performers.
D. Allow the team members to set the tone of the meeting.
E. Discuss issues during the meeting until they are resolved.
Answer: AE
CompTIA JK0-017 JK0-017 exam dumps JK0-017 demo
NO.21 A project is cancelled unexpectedly prior to completion. Which of the following would the project
manager use to document the details of the project closure?
A. Histogram
B. Postmortem
C. SWOT analysis
D. Project scope statement
Answer: B
CompTIA certification training JK0-017 exam JK0-017 practice test JK0-017 JK0-017 JK0-017
NO.22 Which of the following tools is the BEST to measure data organized in time sequence?
A. Run chart
B. Ishikawa diagram
C. Pareto chart
D. Histogram
Answer: C
CompTIA JK0-017 exam prep JK0-017 exam JK0-017 test
NO.23 A project manager needs to identify uncertain events during the planning phase. Which of the following
documents would be the BEST source of this information?
A. Quality log
B. Risk register
C. Issues log
D. Responsibility assignment math
Answer: B
CompTIA braindump JK0-017 answers real questions JK0-017 JK0-017 exam
NO.24 The method of cost-estimating whereby the costs of the individual work packages are aggregated to
form the full cost-estimate is called:
A. parametric estimating.
B. bottom-up estimating.
C. expert judgment.
D. analogous estimating.
Answer: B
CompTIA exam simulations JK0-017 JK0-017 JK0-017 JK0-017 certification
NO.25 Which of the following would be the benefit of saving a project binder in a centralized location?
A. Provides an opportunity for another project manager to review the binder and make corrections.
B. Provides an opportunity for team members to review their contributions.
C. Provides other project managers the opportunity to review the project information.
D. Provides stakeholders the opportunity to modify the change request forms.
Answer: B
CompTIA JK0-017 braindump JK0-017 JK0-017 answers real questions
NO.26 The EV of a particular project is $6 million. The CV is -$340,000. Which of the following can be
determined from this information?
A. The project costs are currently under-budget.
B. The AC is less than the EV.
C. The EV Is higher than the AC.
D. The project costs are currently over-budget.
Answer: D
CompTIA test answers JK0-017 JK0-017 JK0-017 JK0-017
NO.27 In which of the following situations would a risk be placed in the upper right quadrant of a risk matrix?
A. The team identified a risk to have a medium probability of occurrence and a high impact on project
success.
B. The team identified a risk to have a high probability of occurrence and a high impact on project
success.
C. The team identified a risk to have a low probability of occurrence and a high impact on project success.
D. The team identified a risk to have a high probability of occurrence and a medium impact on project
success.
Answer: B
CompTIA test answers JK0-017 JK0-017
NO.28 Two employees will not work on the same project together. The project manager tells the employees to
talk to their supervisors because the supervisors recommended they work together. This is an example of
which of the following conflict resolution styles?
A. Withdrawing
B. Forcing
C. Accepting
D. Compromising
Answer: B
CompTIA certification training JK0-017 test JK0-017 pdf
NO.29 In order to validate a project, which of the following is required to complete a stakeholder analysis?
A. Verify the project stakeholder needs, wants, and expectations are turned into requirements.
B. Verify the project stakeholders have been selected by the project manager to provide the best scope
for the project.
C. Verify the project team members will be able to provide the expected stakeholder results.
D. Verify the project stakeholders needs are documented in the work breakdown structure (WBS)
Answer: D
CompTIA pdf JK0-017 certification JK0-017 JK0-017 JK0-017 test
NO.30 Which of the following shows the number of communication channels for a team with twelve
stakeholders?
A. 56
B. 66
C. 72
D. 132
Answer: C
CompTIA JK0-017 JK0-017 exam simulations JK0-017 practice test
CompTIA JK0-017 exam is a Technical Specialist exam. CompTIA JK0-017 exam can help and promote IT staff have a good career. With a good career, and of course you can create a steady stream of corporate and national interests, so as to promote the development of the national economy. If all of the IT staff can do like this the state will become stronger. IT-Tests.com CompTIA JK0-017 exam training materials can help IT personnel to achieve this purpose. We guarantee you 100% to pass the exam. Make the tough decision to choose our IT-Tests.com CompTIA JK0-017 exam training materials please.
没有评论:
发表评论